Transition notes:
- All the projectile motion equipment (C4) needs to be removed.
- The track and RMS pulley system need to be returned to the position used in Lab 3.
- If on-sequence remember to leave out the large universal clamp used on the catch box, and reurn the pulley system to the large clamp.
Equipment List:
- Pasco 750 Lab interface with the following sensors:
- Pasco 2.2 m track (T2) (elevation clamp on 45 cm rod (A1), small Universal clamp (C20.4) to table)
- RMS pulley system: (See the set up notes for instructions on how to assemble this system.)
- Pasco RMS
- 90 cm rod (A1)
- Large universal clamp (C20.4)
- Smart pulley on 15 cm rod (C10.2)
- 2 Right angle clamps (C10.3)
- String with loops (approximately 2.5 meters long before the loops are tied in the ends, Izorline) (A1)
- Cart masses (C10.1)
- 2-full blocks (approximately 500 g)
- 2-half blocks (approximately 250 g)
- 2-brass posts to hold masses on cart. (A13)
- Mass set (1-10, 2-20, 2-50,1-100,2-200,1-500 gram) (C10.1)
- 50g mass holder (C10.2)
- 5g mass holder (C10.2)
- Electronic balance (A3.3) (attached to lab table shelf)
Notes and tests:
- Start “2305_Lab5_RTP5_test1.ds”. Spin the Rotary Motion Sensor and push and the force probe. It should register on the graph.
- Elevation clamp is not needed, but there is no need to remove it.
- The track and RMS pulley system are set up in exactly the same way as in Lab 3.
- No friction pads are used in this lab.
|


|