|
.bash
include/bfield.inc
gufld.F
uginit.F
You can download the gzipped new map from the document database:
new map
For comparisons:
.euclid
gukine.F
old gufld.F
|
Collimator simulation/design:
Jim Birchall has already looked into our sensitivities for most possible
collimator rotations and translations. We at VT had agreed to look into
rotations as described in Figure 1 below. These are slightly different
rotations than Jim Birchall had done. He
was effectively rotating the collimators about the center
of the target (by changing the beam angle). But, as Jim pointed out,
rotations of the type shown below can be obtained
from a combination of rotations about target center and lateral
displacements.
Juliette is gone for the next three weeks teaching talented high schoolers at Santa Cruz. But thankfully, she left Mark with code set
up to do the collimator rotations described in the figure below. Mark will try to get that done next week.
|
Figure 1 - Roll, pitch and yaw for the 12 o'clock and 6 o'clock octants.
|
|
|
Drift Chamber:
As reported in May, Norm and our spring/summer undergraduate
research assistant Elizabeth Bonnell completed a full-size six plane (xuvxuv)
chamber. The chamber underwent initial testing. Simple wire maps showed
some missing wires and some "hotter than average" wires. The chamber was
returned to the clean room for diagnosis. There was a variety of causes
of the missing channels:
* There was one cold solder joint on the end of a wire and two cold solder
joints on a card edge connector. All the connections had previously been
checked for continuity with an ohm-meter, but these were either missed
or opened up since they were checked. Soldering will be done more carefully
in the future.
* Two dead channels were due to opens on a TDC ribbon cable connector.
* Two dead channels were due to nicked traces on the circuit board that
brings the signal from the sense wire to the edge connector.
* All of the above problems were fixed.
We had the aluminum end-plates Alodined (Chromate coating) with the thought
that it might improve our ground connections (see Figures 2) on the
Faraday cage. The chamber was reassembled and one leak was found at a
circuit board/Ertalyte joint. This was fixed with epoxy. The chamber
has been returned to the test room (see Figure 3) and is presently being
flushed with gas for further testing.
We still see some evidence of induced noise from the DAQ system (it appears
to be our Struck 3100 VME controller). We would like to switch very
soon to a system with the F1 TDCs and a VXI crate. Steve Wood says he has
another VXI crate on order, so it can replace the one he will give us. All
the stuff is available he just needs to collect it up when he gets time,
so we hope to pick the stuff up in the next couple weeks.
Work is still(!) in progress on adapting the HKS/SOS tracking code to
do track reconstruction for our current 6-plane chamber. Mark hopes to be
done with this in the next week.
|
|
Figure 2 - The "golden" chamber with its fresh Alodine coating.
|
Figure 3 - Chamber back in place in the testing area (on the Hokie orange
table).
|
|
Jefferson Lab  |  Virginia Tech Main Page  |  Jefferson Lab's Qweak Page  |  VT Physics
Back to Top  |  Back to Main
Page Maintained by Juliette Mammei Last Update: 11/28/06
Email Juliette     
|

|
|